Saipem has performed a very significant portion of the huge Khurais Field Development program

  • Type of contract: Engineering, Procurement and Construction
  • 2 packages: KCC (Khurais Crude Contract) and KUC (Khurais Water Injection Facilities and Utilities Project)
  • 4 main contracts: KHURAIS CRUDE CONTRACT PROJECT (KCC), KHURAIS UTILITIES CONTRACT (KUC), KHURAIS GAS CONTRACT (KGC), KHURAIS COMMON FACILITIES (KCF)
  • 315Million metric standard cubic feet per daygas production
  • 70Thousand barrels per calendar dayNGL production
  • 1.2million barrelscrude production
  • 12000unitsManpower at peak

The Scope of work

The Khurais Crude contract is part of Aramco's “KHURAIS CRUDE INCREMENT PROGRAM”, completed in 2009. It is made up of two packages: KCC (Khurais Crude Contract) and KUC (Khurais Water Injection Facilities and Utilities Project). The Khurais facilities are completely integrated into the existing network (electricity, data transmission, pipeline, etc.) and are designed to produce 1.2 million barrels of crude from the Khurais, Abu Jifan and Mazalij fields, as well as 315 MMSCFD of gas and 70 MBCD of NGL. The overall project consisted of 4 main contracts:

 

• KHURAIS CRUDE CONTRACT PROJECT (KCC)

• KHURAIS UTILITIES CONTRACT (KUC)

• KHURAIS GAS CONTRACT (KGC)

• KHURAIS COMMON FACILITIES (KCF)

Saipem people on this project

  • Alberto Invernizzi - Project Manager

  • Project time 2006 - 2009